Construction Update
Sedona-Oak Creek Unified School District
Sedona, Arizona
SEDONA RED ROCK HIGH SCHOOL

BIG PARK COMMUNITY SCHOOL
BIG PARK ELEMENTARY SCHOOL: Demolition is complete on Bldgs A & C. Footings have been poured and stem walls started on Bldgs A, C and the new Multi-Purpose building. Demolition of the existing fire lane has been completed and construction of the new fire lane is in progress. The Multi-Purpose and Bldg C masonry wall construction begins late January/early February.
WEST SEDONA SCHOOL
WEST SEDONA SCHOOL: Building 200 footings have been poured and stem walls are complete, slab on grade is scheduled to be poured late January. Building 100 footings are in the process of being poured. Over winter break, gas lines were re-routed and installation of the replacement sewer line was completed. The building will start to take shape as the masonry walls are constructed late January/early February.
For further information on this site or images posted herein, please contact Tara Malloy, McCarthy Director of Client Services, at 480-449-4700.


-481-500.jpg)
-239-400.jpg)