Construction Update

Sedona-Oak Creek Unified School District

Sedona, Arizona

RED ROCK HIGH SCHOOL

  • Red Rock High School - June 2009

    New parking lot is complete

  • Buildings C and D
    • Final finishes are on-going
    • Completes mid-July
  • Fire alarm replacement is on-going
  • Landscaping is under way

Red Rock High School Performing Arts Center & Auxiliary Gym

  • Drawings are into the City for 2nd Review comments
  • Grading is started on the new Auxiliary Gym
  • Demolition has started at the Performing Arts Center and locker room remodel

 

WEST SEDONA

West Sedona - June 2009
  • West Sedona - June 2009

    CAMPUS IS CLOSED TO THE PUBLIC FOR THE SUMMER

  • New Building 200
    • Final finishes are under way
    • Completion scheduled for July 6th
  • Demolition of existing 200 Building to begin late-June
  • New Building 100
    • Final finishes are under way
  • Building 600
    • Interior demolition is complete
    • Plumbing and electrical rough-ins are under way
  • Parking Lot
    • Curb and gutter will be complete by June 12th
    • Site concrete is on-going
  • Landscaping is under way

 

BIG PARK

Big Park - June 2009
  • Big Park - June 2009

    CAMPUS IS CLOSED TO THE PUBLIC FOR THE SUMMER

  • Building A
    • Final finishes are under way
    • Scheduled to complete July 7th
  • Building C New Addition
    • Final finishes are under way
    • Scheduled to complete July 6th
  • Building C Remodel
    • Demolition is complete
    • Mechanical, electrical and plumbing rough-in are under way
  • Building E
    • Final finishes are under way
    • Scheduled to complete July 10th
  • Parking lot and courtyard remodel
    • Parking lot rough grading is complete
    • Curb and gutter work begins June 15th

 

  • June 2009

(R)