Construction Update
Sedona-Oak Creek Unified School District
Sedona, Arizona
RED ROCK HIGH SCHOOL
-
New parking lot is complete
- Buildings C and D
- Final finishes are on-going
- Completes mid-July
- Fire alarm replacement is on-going
- Landscaping is under way
Red Rock High School Performing Arts Center & Auxiliary Gym
- Drawings are into the City for 2nd Review comments
- Grading is started on the new Auxiliary Gym
- Demolition has started at the Performing Arts Center and locker room remodel
WEST SEDONA
-
CAMPUS IS CLOSED TO THE PUBLIC FOR THE SUMMER
- New Building 200
- Final finishes are under way
- Completion scheduled for July 6th
- Demolition of existing 200 Building to begin late-June
- New Building 100
- Final finishes are under way
- Building 600
- Interior demolition is complete
- Plumbing and electrical rough-ins are under way
- Parking Lot
- Curb and gutter will be complete by June 12th
- Site concrete is on-going
- Landscaping is under way
BIG PARK
-
CAMPUS IS CLOSED TO THE PUBLIC FOR THE SUMMER
- Building A
- Final finishes are under way
- Scheduled to complete July 7th
- Building C New Addition
- Final finishes are under way
- Scheduled to complete July 6th
- Building C Remodel
- Demolition is complete
- Mechanical, electrical and plumbing rough-in are under way
- Building E
- Final finishes are under way
- Scheduled to complete July 10th
- Parking lot and courtyard remodel
- Parking lot rough grading is complete
- Curb and gutter work begins June 15th