Buildings C and D

Stucco is complete
Roofing is complete
Drywall is on going
Buildings will complete mid-July

Parking lot work is beginning and completes early June

Red Rock High School Performing Arts Center & Auxiliary Gym

Projects are in permit review, scheduled to start end of May

BIG PARK COMMUNITY SCHOOL

Big-Park-2_May-09

CAMPUS WILL BE CLOSED TO THE PUBLIC FOR THE SUMMER

Building A

Sidewalks start mid-May
Rough framing and electrical are under way
Drywall to begin mid-May
Scheduled to complete July 7th

 Big-Park-1_May-09

Building C New Addition

Sidewalks start mid-May
Scheduled to complete July 6th

Building C Remodel

Scheduled to begin May 26th

Building E

Kalwall and windows are scheduled to be installed
Drywall and paint is ongoing
Scheduled to complete July 10th

Parking lot and courtyard remodel

Scheduled to begin May 26th

WEST SEDONA SCHOOL

CAMPUS WILL BE CLOSED TO THE PUBLIC FOR THE SUMMER

West-Sedona-50709-001-(Medium)

Building 200

Drywall and paint are under way
Stucco is underway, almost complete
Completion scheduled for July 6th

Building 100

Drywall is getting started
Hardscape is just beginning

Parking Lot begins May 26th