Construction Update
Sedona-Oak Creek Unified School District
Sedona, Arizona
SEDONA RED ROCK HIGH SCHOOL
Buildings C and D
Stucco is complete
Roofing is complete
Drywall is on going
Buildings will complete mid-July
Parking lot work is beginning and completes early June
Red Rock High School Performing Arts Center & Auxiliary Gym
Projects are in permit review, scheduled to start end of May
BIG PARK COMMUNITY SCHOOL
CAMPUS WILL BE CLOSED TO THE PUBLIC FOR THE SUMMER
Building A
Sidewalks start mid-May
Rough framing and electrical are under way
Drywall to begin mid-May
Scheduled to complete July 7th

Building C New Addition
Sidewalks start mid-May
Scheduled to complete July 6th
Building C Remodel
Scheduled to begin May 26th
Building E
Kalwall and windows are scheduled to be installed
Drywall and paint is ongoing
Scheduled to complete July 10th
Parking lot and courtyard remodel
Scheduled to begin May 26th