Construction Update

Sedona-Oak Creek Unified School District

Sedona, Arizona

RED ROCK HIGH SCHOOL

Red Rock Nov 09 1

Phase 1 Classroom additions completed August 2009

Red Rock Nov 09 2

Red Rock High School Performing Arts Center & Auxiliary Gym

  • Masonry at the PAC stage is topped out at 65 feet above finish floor
  • Underground utilities are 80% installed
  • Roofing is starting at gymnasium
  • Framing in classroom remodel & gymnasium has begun

 

WEST SEDONA

West Sedona 1

Phase 1 completed July 2009

West Sedona 2
  • Building 300 to be completed by end of year
  • Final finishes are being installed
  • Amphitheater is over 50% complete
  • Site grading & drainage is being addressed

 

 

 

 

West Sedona 3
West Sedona 4

 

BIG PARK

Big park 1

Construction completed July 2009

Big park 2

 

  • November 2009