Allegiant Stadium
Hospitality & Entertainment — Las Vegas, NV

Allegiant Stadium

Allegiant Stadium is the 1.8 million-square-foot world-class home of the NFL’s Las Vegas Raiders and the University of Nevada, Las Vegas (UNLV) college football team. The 65,000-seat facility includes a retractable natural turf field for the NFL, an artificial turf playing surface for UNLV, large operable walls that open to spectacular views of the Las Vegas Strip, a translucent roof, and a variety of premium spaces throughout all levels.

With safety at the forefront, the team relied on the design-build delivery method and technology to drive enhanced decision-making at all facets of the project, ultimately reducing the time and construction cost. The design-build team overcame a host of unique challenges to deliver Allegiant Stadium ahead of schedule.

Visually inspired by the sleek and gradual curves of a futuristic luxury vehicle, Allegiant Stadium is unlike any other venue, making it an architectural and engineering marvel. The unique features of the domed stadium include a cable net truss system used for the roof. The seven-acre ETFE roof is suspended by 100 stainless steel cables that create the light-weight roof structure diaphragm. The translucent roof protects players and fans from the summer heat while preserving the atmosphere of an outdoor stadium.

Meeting the challenge to provide the Raiders with a real grass field in the desert, the facility also features a retractable field system. Weighing nearly 20 million pounds, the playing field is housed in a movable 4-foot-deep “tray” and moves on 540 electrically-powered wheels across 13 rails, which allows the natural grass field to move outdoors for sunlight and water. This feature provides the stadium with the versatility of using both natural grass and artificial turf playing surfaces.

The landmark facility required the removal of 895,000 cubic yards of dirt, the installation of 12 miles of concrete drilled shafts, and miles of piping and utility systems. Nineteen construction cranes were used throughout the project during the installation of 28,000 tons of structural steel, 105,000 cubic yards of concrete and 482,000 structural bolts. The Mortenson | McCarthy joint venture self-performed all structural concrete including foundations, walls, columns, cores, slab on metal deck and slab on grade.

Another unique stadium feature is an 85-foot, 3D-printed torch in honor of former Raiders owner Al Davis, the father of current owner Mark Davis.

The YouTube series From the Ground Up chronicles the stadium’s design and construction, the experiences of the men and women responsible for building it, and the challenges tackled during construction of the ultra-modern stadium.

The team’s commitment to safety was always the No. 1 priority throughout construction. Allegiant Stadium achieved a remarkable safety record with a total recordable incident rate (TRIR) of 0.98, less than one-third the national average. More than 12,000 individuals contributed to the project’s design and construction.

Workforce and business inclusion were key components of this community project. Allegiant Stadium exceeded all small and diverse business goals, with 23 percent awarded to small businesses and 62 percent of the workforce being minority and female.

From the procurement process to training opportunities and student tours impacting the next generation of builders, efforts were focused on the local Las Vegas community. Seventy percent of all firms involved on the project were Nevada-based companies and more than 6 million labor hours went into constructing the project.

Photo Credit: Jason O'Rear

105,000
cubic yards concrete
6
MILLION+
Labor Hours
62%
WORKFORCE
MINORITY & FEMALE
70%
Nevada-Based Businesses Involved

JV Partner

  • Mortenson

Engineers

  • ARUP (Structural)
  • SSR, Inc. (MEP)
  • Kimley-Horn (Civil)

Design Architect

  • Manica Architecture

Architect of Record

  • HNTB

Contact

Jeff Wood

Jeff Wood

Address
2580 St. Rose Parkway
Suite 200
Henderson, NV 89074
Email
Phone
702-990-6707